The Town of Manchester Water Department is in the process of making upgrades to the Globe Hollow Water Treatment Plant. Due to these upgrades, the annual water main flushing program will be moved to Fall 2025.
The Town of Manchester Department of Public Works, Engineering Division proposes to install 5 ft-wide concrete sidewalk on the east and west sides of Keeney Street from the existing end of sidewalk near Nutmeg Drive and Garden Grove Road south to Bush Hill Road and West Gerald Drive.
This project is in part grant funded through the Community Connectivity Grant Program (CCGP) from the Connecticut Department of Transportation (CTDOT). Design and Construction Inspection to be completed by the Town of Manchester Engineering Division.
Schedule
Construction is anticipated to begin in July 2025 and take approximately 5 months to complete.
Keeney St, Manchester, CT 06040 View Map
Keeney St , Manchester, CT 06040